|
HISTORY OF PROPERTY,
OWNERSHIP, AND USE
Prior to 1962, the Marjol property was used for surface and subsurface
coal mining. The Marjol Battery and Equipment Company owned and
operated the recycling facility from 1962 to 1980. The Marjol
operations consisted of lead reclamation from used automotive
batteries. Lead reclamation was accomplished by cutting the batteries
open to remove the lead plates, discarding the acid in the battery and
crushing the casing. At times, lead posts and connectors were removed
from the top of the battery, melted and formed into ingots. The
crushed casings were placed in a former drainageway and strip pits
left from the past mining. Later in the operations, when the
composition of the casings changed, the casings were recycled.
As a result of these lead reclamation operations, a large volume of
battery casing material and soil (both on-site and off-site) became
contaminated with lead. The total estimated volume of soils and
battery casings exceeding the Site clean-up level of 500 milligrams
per kilogram (mg/kg) lead is approximately 372,000 cubic yards.
Gould purchased the Marjol Battery and Equipment Company in May of
1980. Shortly thereafter, Gould began to phase out plant operations
and ceased operations completely in April 1982. During the period from
1988 through 1992, the off-site impacts on nearby residential
properties and drainage ways were addressed by excavation of soils
with lead concentrations above 500 mg/kg. The majority of the
excavated soils have been contained on the site since that time. In
1989 and 1990, the ground surface of the
site was significantly
modified by Gould during stabilization efforts designed to prevent
migration of contaminants. Windblown dust is controlled by the
pavement and grass that cover large areas of the Facility. Surface
water runoff is discharged in a controlled manner through a stormwater
management basin. Direct contact with soil containing lead has greatly
been reduced by fencing the Facility and an area northeast of the
Facility, and by providing Site security.
Click here for a map of the Marjol
Site.
Go to Top of Page
REGULATORY HISTORY AND CURRENT SITE STATUS
The Site has been the subject of several consent orders under both the
US Environmental Protection Agency’s (USEPA’s)
Comprehensive Environmental Response, Compensation and Liability Act
(CERCLA) and its
Resource Conservation and Recovery Act (RCRA) programs. The final
remedy for the Site is being addressed under USEPA’s RCRA Program.
Go to Top of Page
CERCLA 1988 CONSENT
ORDER
On April 6, 1988, Gould and the USEPA entered into a Consent Agreement
and Order to perform emergency removal actions under Section 106(a) of
CERCLA. The CERCLA 1988 Consent Order removal action was to secure and
stabilize the Facility, and to identify and address the contamination
in the nearby residential areas. The CERCLA 1988 Consent Order also
required that the extent of contamination on-site and off-site be
determined. The activities required by the CERCLA 1988 Consent Order
have been completed; these activities included soil removal and
restoration of 133 properties, interior house cleaning of 107
residential units, an extent of contamination study and site
stabilization to control off-site migration of lead.
Go to Top of Page
RCRA 1990 CONSENT
ORDER
On June 11, 1990, an Administrative Order on Consent (RCRA 1990
Consent Order) between the USEPA, PADEP and Gould was signed regarding
the Site. The 1990 RCRA Consent Order required Gould to conduct a RCRA
Facility Investigation (RFI) and a Corrective Measures Study (CMS).
The activities required by the RCRA 1990 Consent Order have been
completed.
On October 15, 1999, the USEPA and PADEP issued a Statement of Basis
(USEPA 1999) for the Site; this was USEPA and PADEP’s proposed remedy
for the Site that called for, among other measures, on-site
containment of the battery casing material that had been placed in the
former drainageway. Extensive comments were submitted on the proposed
remedy in the Statement of Basis during the public comment period from
November 1, 1999 through January 18, 2000. During the public comment
period, questions were raised by a consultant to the Borough of Throop
regarding the condition of two coal seams that underlie the battery
casing material that was proposed to be left on-site. These two seams
are called the Top Split of the Top Four-Foot and the Top Four-Foot
seams, and the questions focused on whether or not they had been mined
and whether they pose a mine fire hazard to the battery casing
material.
Go to Top of Page
USEPA/PADEP’s FINAL DECISION ON A REMEDY FOR THE SITE
On December 4, 2000, the USEPA in conjunction with PADEP issued its
Final Decision on a
remedy for the Site. That remedy consists of the following
corrective
measures (click here to
see a schematic of the site after the cleanup):
- Excavation of soil and battery casings from on-site areas north of
the southern most limit of the General Five-Foot coal seam, which
exceed the soil lead cleanup standard of 500 mg/kg. This material will
be consolidated on-site or removed for off-site disposal as described
below;
- Excavation of soil with lead concentrations exceeding 500 mg/kg in
the North Woods, and wooded areas adjacent to the Woodlawn Street
playground and consolidation on-site or off-site disposal as described
below;
- Solidification of the upper most layer of contaminated material
beneath the RCRA cap;
- Construction of a cap on top of the contaminated material remaining
on-site that complies with applicable federal and state standards;
- Off-site disposal of all contaminated soil and waste material
exceeding 500 mg/kg lead which cannot be consolidated beneath the cap
as determined by the Final Design;
- Use of dust control measures to prevent the off-site migration of
contaminated soil during remedial activities;
- Modification of the Stormwater Management Basin to ensure that it is
effective in preventing releases of contaminants to the Lackawanna
River during the implementation of the Final Remedy;
- Imposition of institutional controls such as use restrictions, title
notices, and proprietary controls, to ensure that the cap integrity is
maintained;
- Implementation of Site-wide operation and maintenance activities
during and following implementation of the remedy for the Site,
including operation and maintenance of the Storm Water Management
Basin to prevent releases of lead and other contaminants to the
Lackawanna River during remedial activities; and,
- Confirmatory sampling for the following media:
- soil sampling for lead, PAHs, and PCBs to confirm that soil cleanup
standards are achieved on-site;
- monitoring of sediments in the Lackawanna River;
- off-site sampling to ensure that remedial activities have not caused
off-site contamination and corrective action if necessary; and,
- groundwater monitoring to continue for an unspecified period to
ensure that contaminants are not released following implementation of
the remedy.
Go to Top of Page
Click here to see a
cross-section of the coal seams and the capped area after the cleanup
is complete.After the Final Decision was issued, there was an extensive review of
USEPA’s selection of corrective measures for the site by the USEPA’s
National Ombudsman. After reviewing available documents; meeting with
the USEPA Region 3, PADEP (including the Bureau of Abandoned Mines and
Reclamation), Gould, and AGC, the National Ombudsman made the
following recommendations:
- Calculate the surface strains from any expected subsidence and
design and implement the cap to meet or exceed those calculations to
make a more reliable cap.
- Work with Gould, PADEP, and the Borough of Throop to reach
agreement on the method, such as borehole drilling, to properly
address the safety issue of potential mine-fire hazard associated with
the Top Split of the Top Four Foot Coal Seam and Top Four Foot Coal
Seam on the Site.
Click here to view the
entire report of the Ombudsman Review of the Marjol Battery Site.
These recommendations are being implemented under the Corrective
Measures Implementation Consent Order.
Go to Top of Page
RCRA 2006
CONSENT ORDER
On July 13, 2006, a new Administrative Order on Consent (RCRA 2006
Consent Order) signed by the USEPA, PADEP and Gould became effective
regarding the implementation of Corrective Measures at the Site.
The RCRA 2006 Consent Order
lays out the requirements for implementing the corrective measures in
USEPA/PADEP’s Final Remedy.
Go to Top of Page
CORRECTIVE MEASURES WORK PLAN SUBMITTAL AND APPROVAL
The signing of the new Consent Order was the first step in the
Corrective Measures Implementation (CMI) Process. The next step was
submitting the draft CMI Work Plan to USEPA and PADEP which occurred
on July 21, 2006. The Work Plan provides a history of the site, and
spells out how the design of the remedy will proceed. The CMI Work
Plan (with revisions) was approved by USEPA and PADEP on May 3,
2007, with the exception of Section 7.5, Institutional Controls. Section 7.5,
Institutional Controls, was issued and approved as final by USEPA on
May 29, 2007.
Go to Top of Page
PRE-DESIGN INVESTIGATION
The CMI Work Plan included a Work Plan for a Pre-Design
Investigation. The Pre-Design Investigation (PDI) was intended to
supplement previous studies conducted at the Site to aid in
designing the remedy for the Site.
The PDI was divided into three separate investigations with each
having specific objectives as follows:
1) Supplemental Mine Fire Investigation
- The Supplemental Mine Fire Investigation took
place between September 11, 2006 and October 13, 2006 under the
supervision of geologists from AGC, USEPA, and Gannet Fleming (Skelly
& Loy) for PADEP.
The investigation
yielded information that will be useful in the design of the final
remedy; two additional borings were added to further investigate the
limit of the Five Foot coal seam. Gould submitted its conclusions on
the investigation to the USEPA and PADEP on October 30, 2006.
(Click here to review the Supplemental Mine Fire Investigation
Summary Report).
On December 18, 2006, USEPA, PADEP, and
Gannett Fleming provided comments on the Supplemental Mine Fire
Investigation Report to Gould. USEPA also
provided a Fact Sheet Update regarding the site on December 18,
2006. (To view USEPA's Fact Sheet Update, click here). In the fact
sheet, USEPA states that the EPA and PADEP technical review teams
have evaluated the new and previously existing data related to the
coal seams and that all review parties, including the Gannett
Fleming oversight team, agree with the following conclusions:
-
The Top Four Foot Coal Seam and the Top Split Top Four Foot Coal
Seam do not pose a mine fire hazard to the waste containment area
proposed for the site;
-
A waste containment area may be designed with adequate isolation
from the Five Foot coal seam.
2) Depth to Bedrock Investigation
- The Depth to Bedrock Investigation was completed
during the week of November 27, 2006. The study determined the depth
to bedrock in the area of the proposed relocated Stormwater Basin,
northwest of the existing Stormwater Basin.
3) Supplemental Soil Investigation
- The Soil Sampling Investigation was conducted
from April 19, 2007 to May 25, 2007and was completed on August 7 and
8, 2007. The objective of this investigation was to further
delineate the vertical and horizontal extent of impacted surface
soils and to define wooded areas requiring clearing and excavation.
The areas sampled during the PDI include:
- The North Woods;
- The North Ravine;
- Southwest of the North Woods;
- The former Throop Borough Woodlawn Street property;
- Grove Street and the entrance road; and,
- The trailer area.
The data from the soil sampling investigation was used to determine
the horizontal and vertical limits of excavation presented in the
Preliminary Design.
Click here
to view the horizontal limits of
excavation as determined by the sampling.
Go to Top of Page
30%
DESIGN SUBMISSION
Gould submitted the 30% Design to USEPA and PADEP on June 29,
2007. The 30% Design Submission presented Gould’s preliminary proposal on how the Final Remedy would take
place, what would be done, and what the Site would look like after the
remedy is implemented. The 30% Design Submission included Gould’s preliminary proposal for
several items such as:
- What the size of the capped area will be and where it will be
located on the Site;
- Where the Stormwater Management Basin will be relocated to;
- The Cap Strain analysis that was required by the Ombudsman’s
Report;
- The results of the Pre-Design Investigations;
- Proposed design for achieving isolation between the Five Foot Coal
Seam and materials in the Containment Area;
- Preliminary Construction Drawings and sketches; and
- A Preliminary Construction Schedule.
Gould received
comments from USEPA/PADEP on all but the sampling and analysis
portions of the 30% Design on August 10, 2007. Gould responded to USEPA/PADEP's
comments on September 7, 2007. USEPA/PADEP
Comments on the sampling and analysis portion of the 30% Design were
received on October 4, 2007.
Gould responded to USEPA/PADEP's
comments on the sampling and analysis portion of the 30% Design on
November 28, 2007. USEPA/PADEP's October 4, 2007 Comments and
Gould's November 28, 2007 responses were added to the 90% Design
Document.
Go to Top of Page
90%
DESIGN SUBMISSION
Gould submitted the Pre-Final (90%) Remedial Design (represents
about a 90% level of completion) to USEPA/PADEP on November 8, 2007.
Gould received comments on the 90% Design (other than the sampling
and analysis section) from USEPA/PADEP on December 13, 2007.
Comments from USEPA/PADEP on the sampling and analysis section were
received on February 1, 2008. Gould submitted responses to USEPA/PADEP’s
comments on the 90% Design to USEPA/PADEP on March 12, 2008.
100%
DESIGN SUBMISSION
Gould submitted the Final (100%) Design USEPA and PADEP on April
11, 2008. The 100% Design Plan was approved by USEPA/PADEP on
May 8, 2008. (For more information on
the 100% Design, please click here.)
Click here to learn more about current project information and the Schedule
|