Marjol Battery Site
Spring site maintenance activities to begin end of week of April 29, 2013.
 
Home

Site Background

Summary of Corrective Measures Implementation (CMI) Process

Post-Construction  Maintenance and Monitoring

Construction  Information (May 2008 to August 2010)

Final (100%) Remedial Design

Air Monitoring

Stormwater Management System

Photo Gallery

Quarterly Progress Reports - CMI Completion Report - Biennial Report 

Community Relations

Documents

FAQs

Contact Us

Web Site Map

Basin Conversion (summer 2012)

A quarterly inspection of the Marjol Battery Site was conducted on June 27, 2012. Based upon the inspection, Lackawanna County Conservation District (LCCD) approved moving forward with conversion of the sedimentation basin at the Site to a stormwater management basin.   Construction activities associated with conversion of the basin began on July 9, 2012, and were completed on September 12, 2012.


Why did basin conversion need to be done? The temporary sedimentation basin was designed to manage sediment that was picked up in stormwater during construction activities by using structures such as a baffle and skimmer to encourage sediment to drop out and stay in the basin. The basin also always had a few feet of water in it. Once construction activities were complete and vegetation was sufficiently established at the Site, sediment was no longer picked up by the stormwater runoff and the controls were no longer needed. This meant that the basin could be converted to a permanent stormwater management basin which slows down the water but does not retain it. The sediment control structures are no longer present in the stormwater management basin.
 


What was involved in basin conversion? Basin conversion involved several steps:

1) The first step was to dewater the sedimentation basin.


2) Once the water was removed from the sedimentation basin, a ramp was constructed into the basin so that the sediment could be removed. 

3) During basin conversion, the sedimentation basin was backfilled with about 4 feet of soil to an elevation of 752 ft. The permanent stormwater management basin was designed as required by state and local regulations to manage a 2 through 100-year, 24-hour storm event. In addition, the permanent stormwater basin meets the Throop Borough Stormwater Management Ordinance that requires that a minimum 1-foot freeboard is maintained for a 2 through 100-year storm event.

4) The skimmer was removed from the outlet structure, two permanent bottom orifice plates were installed on the outlet structure to allow water to discharge from the basin at a controlled rate, some additional gabion mattresses were installed as energy dissipaters at the bottom of both the north and south channels with additional riprap was placed at the bottom of the north channel.

5) Finally, topsoil was placed over all disturbed areas and the areas were seeded and fertilized in order to establish vegetation.



Was contaminated material disturbed during basin conversion? During the basin conversion process, disturbance of the contaminated material that is inside the capped area did not occur. Construction activities for basin conversion only involved activities in areas and with materials (soils/sediments) that are “clean” (average lead levels below 500 mg/kg).



How was stormwater managed during the basin conversion process? During basin conversion, when there was a heavy storm and discharge from the basin occurred, a turbidity measurement was taken as soon as practicable (i.e., during the next scheduled working hours). It was expected that if there was stormwater discharge during the basin conversion activities, the turbidity level would exceed the 250 NTU standard that was set for the Site as an indirect measurement of dissolved lead while contaminated materials were being handled. LCCD, PADEP, and USEPA were all aware that the turbidity level for the Site would likely be exceeded when stormwater discharge occurred before vegetation was established in the basin. It was agreed that while construction activities were occurring for basin conversion, stormwater discharge samples would be collected and analyzed for total and dissolved lead if there was a turbid discharge. (Note: As approved by PADEP, if there was a multi-day turbid discharge event, a sample would only be collected on the first day of turbid discharge.) Once earth moving activities were complete and the topsoil was seeded with erosion control mat in place, no discharge monitoring would take place.

Note: During basin conversion, a discharge sample was collected on July 27, 2012.  See the Stormwater Management System July calendar page for sample results.  (Click here to go to the Stormwater Management System July calendar page.)



What happens after basin conversion (including, how will stormwater be managed post basin conversion)? Now that basin conversion is completed, erosion inspections focusing on erosion and sedimentation controls will continue until permanent vegetation is established on the newly seeded areas. Once that vegetation is established, Gould will request an inspection by LCCD to close out the NPDES permit for the Site. The earliest that this will occur is after the fall growing season 2012. Until that time, Gould has elected to continue basin discharge sampling for total and dissolved lead on a monthly basis, as possible, following heavy rain events. With the change from a sedimentation basin to a stormwater management basin, stormwater is no longer stored in the basin and the water can discharge on its own such that discharge from a storm event may be completed by the time personnel report to the Site and consequently we may not be able to obtain samples. Please note, no sampling will take place during a rain event.

 

(Click here to go back to the Stormwater Management System page.)

 

Page Last Modified Tuesday September 18, 2012 12:38:50 PM

 

tel 570.383.9313 | email layers@advancedgeoservices.com

Send mail to
agc@advancedgeoservices.com with questions or comments about this web site.
Copyright © 2006 Advanced GeoServices