As
a result of heavy rains in July and August, 2009, water overflowed
the Containment (cap) Area (CA) (which has contaminated material in
it) into a drainage feature (the South Swale) outside of the CA and
into the basin on July 31, August 10, and on August 12, 2009. While
every effort has been made to keep this type of overflow from
occurring, the possibility of it happening was considered in the
design, and so the overflow water flowed into the sediment basin as
it is supposed to do where the lead contaminated sediment could
settle out before the water is discharged. Tests conducted after the
overflows show that the discharges were well below the limits that
were set by the State to protect the Lackawanna River.
When each of the overflow incidents has occurred, the skimmer in the
basin has been raised (if it wasn’t already) to prevent the flow of
water from the basin through the discharge channel. Water in the
basin was tested for turbidity and when it was below the performance
standard, the skimmer was lowered to allow water to discharge.
After the overflow in July, the basin water was also tested for
total and dissolved lead. Any sediment and battery casings that have
floated onto the CA berm and into the swale were removed and placed
back into the CA. XRF analysis (an XRF is a portable instrument used
for testing lead concentration in substances such as soil) for lead
has been performed on the berm and in the swale to see if the
overflow contaminated any previously clean areas.
If
the soil lead levels were above the cleanup level, then soils on the
berm and swale were excavated and placed into the CA. The excavated
areas were rechecked with the XRF to be sure lead levels were below
the cleanup standard.
After the first overflow, a meeting was held to discuss how to
better control an overflow if it happened again. In order to get
more room to hold the contaminated water so that it would not go
off-site, it was decided to pump the contaminated water from the CA
to a strip pit that was previously excavated – Area B – instead of
back into the CA as the practice had been. Area B was tested near
the end of the project and was re-excavated with the
contaminated material being placed in the CA and solidified.
Subsequent efforts after the overflows focused on making sure that
the pumps were ready when rain occurred during the night and that
the pumps could handle all of the water. While the overflows are not
what we would like to see, the important point is that the lead is
being contained within the site as it is supposed to be while we are
managing the water as best we can with the unfavorable weather we
have been having.
Reports with the details of the overflows have been submitted to EPA
and DEP. Click on the links below to review the reports.
Report on July 31, 2009 Overflow
Report on
August 10 and 12, 2009 Overflows