Marjol Battery Site
 
Home

Site Background

Summary of Corrective Measures Implementation (CMI) Process

Construction Schedule and Information

Final (100%) Remedial Design

Air Data

Photo Gallery

Quarterly Progress Reports & Monitoring

Community Relations

Documents

FAQs

Contact Us

Web Site Map

Summary of Corrective Measures Implementation (CMI) Process
  • Consent Order Signed
  • Corrective Measures Implementation Work Plan Submitted
  • CMI Work Plan Approval
  • Preliminary Design Investigation
  • Preliminary (30%) Design Submitted
  • Pre-Final (90%) Design Submitted
  • 100% Design Submitted
  • Contractor Selection Process
  • Construction of Final Remedy
  •  

    The following provides an outline of the CMI Process that we have been following.  (Click here to view a flow chart outlining the CMI Process.)

    Consent Order Signed On July 13, 2006, a new Administrative Order on Consent (RCRA 2006 Consent Order) signed by the USEPA, PADEP and Gould became effective regarding the implementation of Corrective Measures at the Marjol Battery Site. The RCRA 2006 Consent Order lays out the requirements for implementing the corrective measures in USEPA/PADEP’s Final Remedy.  The first phase is the design phase and the second phase is construction.  The third and final phase is maintaining and monitoring the constructed remedy.

    Corrective Measures Implementation Work Plan Submitted – July 21, 2006
    The CMI Work Plan was due to be submitted by Gould to the Agencies within 60 days after the Consent Order was signed. In an effort to move the process forward and allow the pre-design investigation to occur this construction season, Gould was able to submit the Work Plan early.

    CMI Work Plan Approval - May 3, 2007; Section 7.5 on May 29, 2007
    On May 3, 2007, USEPA and PADEP approved the Marjol Corrective Measures Work Plan (with revisions) with the exception of Section 7.5, Institutional Controls. Section 7.5, Institutional Controls, was issued and approved as final by USEPA on May 29, 2007. 

    (Please note that the Supplemental Mine Fire Investigation portion of the Preliminary Design Investigation was previously approved on September 1, 2006; the Depth to Bedrock Investigation was previously approved on November 2, 2006 . 
    These investigations were approved in order to allow for those parts of the PDI to occur in the Fall of 2006.  The Soil Sampling Investigation Plan was approved on April 20, 2007, allowing soil sampling to begin on April 23, 2007.)

    Preliminary Design Investigation - September 11, 2006 to August 8, 2007
    The Supplemental Mine Fire Investigation portion of the PDI began on September 11, 2006 and was completed on October 13, 2006.  The Depth to Bedrock Investigation was completed during the week of November 27th along with soil samples that were obtained using the same type of equipment. The Soil Sampling Investigation was conducted from April 19, 2007 to May 25, 2007and was completed on August 8, 2007. 
    (Click here for more information on the PDI Investigation.)

    Preliminary (30%) Design Submitted - June 29, 2007
    Although the Preliminary or 30% Design Submission was not due to USEPA and PADEP until 90 days after all phases of the PDI were completed, in an effort to facilitate the start of construction in Spring 2008, Gould submitted the 30% Design on June 29, 2007.

    Gould received comments from USEPA/PADEP on all but the sampling and analysis portions of the 30% Design on August 10, 2007.  Gould responded to USEPA/PADEP's comments on September 7, 2007.  USEPA/PADEP Comments on the sampling and analysis portion of the 30% Design were received on October 4, 2007.

    Pre-Final (90%) Design Submitted - November 8, 2007; Sampling & Analysis Portion on November 28, 2007
    The Pre-Final (90%) Design Submission was submitted to USEPA and PADEP on November 8, 2007.  Gould's responses to USEPA/PADEP's comments on the sampling and analysis portion of the 30% Design were submitted to USEPA/PADEP on November 28, 2007 and were added into the Pre-Final Design Document. Gould received comments on the 90% Design (other than the sampling and analysis section) from USEPA/PADEP on December 13, 2007. Comments from USEPA/PADEP on the sampling and analysis section were received on February 1, 2008.

    100% Design Submitted – April 11, 2008
    The 100% Design Submission was submitted to USEPA and PADEP on April 11, 2008.  The 100% Design Plan was approved by USEPA/PADEP on May 8, 2008.

    Contractor Selection Process – started November 15, 2007; contractor announced April 25, 2008
    SCE Environmental Group of Dickson City, PA, was chosen and approved by USEPA/PADEP as the contractor to perform the construction of the Final Remedy. 
    (Click here to be taken to SCE Environmental Group’s web site).

    Construction of Final Remedy – started May 12, 2008

    Construction of the Final Remedy is expected to take approximately 2 years. We will revise this summary and anticipated dates as the process proceeds forward.

    For more information on the Construction Activities and Schedule, click here.

    For more information on the Background of the Marjol Site, click here.

     

    Check back periodically to learn about upcoming phases of work.

    Page Last Modified Monday October 13, 2008 01:21:43 PM

     

    502 George Street | Throop, PA 18512 | tel 570.383.9313 | fax 570.383.9309 | email layers@advancedgeoservices.com

    Send mail to
    agc@advancedgeoservices.com with questions or comments about this web site.
    Copyright © 2006 Advanced GeoServices