Marjol Battery Site
 
Home

Site Background

Summary of Corrective Measures Implementation (CMI) Process

Post-Construction  Maintenance and Monitoring

Construction  Information (May 2008 to August 2010)

Final (100%) Remedial Design

Air Monitoring

Stormwater Management System

Photo Gallery

Quarterly Progress Reports and CMI Completion Report 

Community Relations

Documents

FAQs

Contact Us

Web Site Map

STORMWATER DISCHARGE ABOVE THE PERFORMANCE STANDARD – JULY 19, 20 and 21, 2010

USEPA, PADEP, and Throop Borough were kept informed on stormwater management activities during the period from July 19 to August 2, 2010.  A formal non-compliance report covering the period from July 19 to August 2, 2010 was submitted to PADEP on August 4, 2010.  (Click here to review the July 19, 2010 Non-Compliance Report.)

July 19, 2010 - On July 19, 2010, after a heavy storm in the late afternoon (over 1.5 inches of rain was received on July 19, 2010), there was a stormwater discharge above the performance standard.  The skimmer was in the discharge position in accordance with the Stormwater Management Design Plan.  After the heavy rainfall, AGC took a turbidity reading at the discharge point and the turbidity meter gave an “Error” message indicating that the levels were above the range of the instrument.   (Turbidity is a measurement of the cloudiness of the water which is caused by sediment.)  The skimmer was flipped to discontinue flow from the basin and a flocculant (Pond-Clear) was added to the basin to enable the sediments to settle out of the water to the bottom of the basin.  Samples of the discharge were taken for the monthly total and dissolved lead analysis.  The dissolved lead result was below the laboratory detection limit of 1.0 ug/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L. The total lead result was 368 ug/L. There is not an NPDES standard for total lead.  The very low total and dissolved lead results provide reassurance that even though the turbidity levels were above the performance standard, there was NOT a release of lead from the site that would affect the creek or the river.

July 20, 2010 - On the morning of July 20, 2010, between 7:13 AM and 7:40 AM, the water in the basin appeared clear, and several readings were taken on the western side of the basin as follows:

69.8 NTU, 116 NTU, 92 NTU, 120 NTU, 122 NTU, 83.8 NTU, 99.1 NTU, 92.7 NTU, 117 NTU, and 89.8 NTU                                   

Based on these readings, the skimmer was flipped at 8:28 AM.  After water reached the discharge point at the perimeter fence, two readings were taken at the fenceline at 8:40 AM.  The results were 61.4 NTU and 79.0 NTUs.  The 200 NTU standard was checked as well and read 197 NTU. In early afternoon (2:10 pm), AGC checked the basin again.  The basin and the discharge appeared turbid.  A turbidity reading of 2292 NTUs was obtained at the discharge point.  The skimmer was again flipped to stop flow.  Additional Pond Clear was added to the basin to further expedite sediments settling out of the water. 

July 21, 2010 - On July 21, 2010, additional turbidity readings were collected in the basin between 3 and 6 inches below the water surface. All readings in the basin were in the 40 NTU range. Based on these readings, the skimmer was flipped to allow discharge from the basin.  Turbidity readings were once again collected at the discharge point immediately following discharge from the basin. Visual observations at the discharge pipe showed clear water consistent with the basin readings. However, the initial turbidity reading was 290 NTUs.  After one minute of flow, the turbidity reading at the discharge point dropped to 190 NTUs.  It is possible the initial 290 NTU reading at the discharge point was due to sediment within the discharge channel.  A third turbidity reading was collected at the discharge point 10 minutes later; the reading was 140 NTUs. Approximately a half-hour later the discharge turbidity reduced to 16 NTUs.  Based on these readings, discharge was allowed to continue with periodic monitoring until approximately 45 minutes later when the turbidity increased to 390 NTUs.  The skimmer was then flipped again to prevent discharge from the basin. Further investigation revealed that the basin water is clear in the top few inches, but below that the turbidity is much higher indicating the Pond Clear is working, but that additional “doses” are needed.  Samples for total and dissolved lead were collected on July 21, 2010.  Two sets of samples were collected: one when turbidity was low and one when turbidity was high.  The dissolved lead results were both below the laboratory detection limit of 1.0 ug/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L. The total lead results were .91 ug/L and 38.3 ug/L, respectively. There is not an NPDES standard for total lead. The very low total and dissolved lead results provide reassurance that even though the turbidity levels were above the performance standard, there was NOT a release of lead from the site that would affect the creek or the river. 

Additional Pond Clear was added to the basin on July 22, 2010.  

Note: Due to questions on the accuracy of the initial turbidity meter being used, a second meter was sent to the Site and is now being used.

 

(Click here to go back to the July 2010 stormwater calendar page.)

 

Page Last Modified Tuesday October 19, 2010 01:48:22 PM

 

 

 

 

 

 

 

 

 

 

tel 570.383.9313 | email layers@advancedgeoservices.com

Send mail to
agc@advancedgeoservices.com with questions or comments about this web site.
Copyright © 2006 Advanced GeoServices