Chipping trees from new sedimentation basin area - 6/2/08
Wood chips from felled trees - 6/2/08
Storage area demolition - 6/4/08
Access road cut into hillside north of existing basin for water truck access - 6/5/08
Decontamination pad construction northwest of existing sedimentation basin on haul road - 6/9/08
Grubbing area northwest of existing basin - 6/4/08
Grubbing at area around basin discharge - 6/3/08
Proposed basin grading - 6/11/08
Storage area demolition - 6/13/08
Stripping and grading area northwest of the existing basin - 6/10/08
Diversion berm installed to direct runoff to western decon pad - 6/12/08
View of site looking east from bottom of basin haul road - 6/13/08
Dust suppression during hillside stripping activities north of the existing basin - 6/16/08
Basin key trench (trench that will anchor the berm of the new basin to the existing soil) filled and compacted to existing grade - 6/17/08
Real-time Dust Monitor - 6/18/08
Extension added to the top of monitoring well (MSB-1) - 6/17/08
Stripped hillside north of existing basin - 6/16/08
Abandoned water main removal in new basin area - 6/19/08
Aerating the compacted fill in the proposed basin to dry out the material for acceptable compaction - 6/20/08
Basin key trench (trench that will anchor the berm of the new basin to the existing soil) extension in new basin - 6/16/08
Viw of new sedimentation basin construction area from the hillside north of the existing basin - 6/19/08
Covering topsoil stockpile and installing silt fence - 6/23/08
Temporary chain link fence installation along western (Lackawanna River side) perimeter - 6/23/08
View of new sedimentation basin construction from hillside north of existing basin - 6/30/08