| |||||
|
Post-Construction Maintenance and Monitoring A Final Inspection was conducted at the Marjol Battery Site on August 31, 2010. Based on the inspection, construction of the Final Remedy was determined to be “substantially complete” as of August 27, 2010, and the site is in the post-construction period. All lead-contaminated material at the Site has been consolidated in the Containment (cap) Area (CA) and covered by the multiple layers of cap materials, so all surfaces of the Site are clean (average lead levels below 500 mg/kg). (Click here for a drawing showing the layers of the cap.) Activities at the Site have now become limited to those associated with Site inspections, monitoring, and the establishment of vegetation. Conversion of the sedimentation basin at the Site to a stormwater management basin is expected to take place in the summer of 2012. In the meantime, Gould will continue to maintain and monitor the Site. With major construction activities at the Site completed, there are several post-construction items Gould would like to provide information to the community about:
FALL/WINTER 2011- 2012 SITE
ACTIVITIES
SITE
APPEARANCE Fencing— A split-rail fence with wire mesh was installed on-site around the Containment (cap) Area (CA) and along the eastern property line to protect the vegetation on the CA and, to prevent motorized vehicle access and to deter pedestrian access. Temporary fence panels were removed from the Site and chain link fencing was installed in some areas to deter motorized vehicles from accessing the property until significant vegetation is established. There is no longer a 6-foot chain link fence around the perimeter of the Site.
POST-CONSTRUCTION INSPECTIONS AND MONITORING The USEPA/PADEP-approved 100% Design Plan includes required elements such as quarterly river monitoring, annual groundwater sampling, and the frequency of inspections. Post-Construction Inspections Representatives from Advanced GeoServices will continue to be available on a daily basis and at the Site on a regular basis. Weekly erosion inspections will take place while the NPDES Permit for the Site is in place (at least summer 2012) unless the ground surface is frozen and/or snow covered. Formal monthly inspections took place in 2010, occurred quarterly in 2011, and will now take place semi-annually through at least 2014. The weekly erosion inspections focus on erosion and sedimentation controls, stormwater management features, discharge sampling if applicable, general site conditions, and site security. (Click here for the current calendar of inspections.) Click on the dates below to review the monthly/quarterly inspection reports:
(Click here to view photos of post-construction Site conditions.)
Special Post-Earthquake and Storm Event Inspection - 2011 In response to the August 2011 earthquake and subsequent heavy rain events (Hurricane Irene and Tropical Storm Lee), Advanced GeoServices conducted a special inspection of the Containment Area (CA) on October 7, 2011. Based on observations of the slope conditions, it is Advanced GeoServices' opinion that the stability of the CA slopes were not adversely impacted by the earthquake or subsequent storm events. (Click here to review the special inspection report.)
See the table below for a list of some of the monitoring activities required in the Design Plan. Summary of Post –Construction Monitoring Activities
NORTH WOODS
LOW AREA MODIFICATIONS
Post-Construction Maintenance and Monitoring Calendar - February 2012
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|