Marjol Battery Site
Spring site maintenance activities to begin end of week of April 29, 2013.
 
Home

Site Background

Summary of Corrective Measures Implementation (CMI) Process

Post-Construction  Maintenance and Monitoring

Construction  Information (May 2008 to August 2010)

Final (100%) Remedial Design

Air Monitoring

Stormwater Management System

Photo Gallery

Quarterly Progress Reports - CMI Completion Report - Biennial Report 

Community Relations

Documents

FAQs

Contact Us

Web Site Map

Stormwater Discharges Above the Performance Standard Post-Construction     (August 27, 2010 to October 16, 2010) 

In addition to being part of the 100% Design Plan for the Site, the stormwater management system at the Marjol Battery Site is maintained and monitored under a permit (NPDES permit) issued by the State of Pennsylvania (Gould Electronics Inc. and SCE Environmental are co-permittees on the NPDES permit for the Site.) The 100% Design Plan called for stormwater discharge monitoring from the Site to be discontinued at the end of construction because at that point the potential for lead to be discharged from the Site was removed. However, the state permit for the Site will remain active until vegetation is established at the Site., On January 27, 2011, PADEP clarified its requirements for basin discharge monitoring while there is limited site activity, BMPs are in place and the permit is still active.   (Click here to review PADEP’s response letter.)  The letter stated that stormwater discharge monitoring is not required on “non-working” (days when there is no earth moving activities).  Note that Gould has elected to continue monthly sampling for total and dissolved lead, even though the potential for lead contamination had been removed now that the remedy is complete.

Prior to receiving the January 27, 2011 letter from PADEP, Gould followed the same protocols for sampling the basin discharge that were in place during construction. (Click here for an explanation of the procedures in place during construction.)  After Substantial Completion was achieved on August 27, 2010, there was a period of discharge above 250 NTUs that is further described below.

(Click here to go back to the Stormwater Management System page.)

 

STORMWATER DISCHARGE INFORMATION SEPTEMBER 30, 2010 to OCTOBER 16, 2010 INCLUDING DISCUSSIONS ON DISCHARGES ABOVE THE PERFORMANCE STANDARD

A substantial rain event, one that has a 2% chance of occurring in any year (commonly referred to as a 50-year storm) occurred September 30 to October 1, 2010 delivering approximately 4.98 inches of rain to the Marjol Battery Site and the surrounding area (based on weather information from the Avoca, PA airport).  According to the Jermyn gauging station, approximately 5.52 inches of rain fell in 24 hours.  Gould inspected the site several times throughout the rain event and did not observe any major erosion issues on the site. The sedimentation basin functioned as designed throughout the rain event. Gould monitored the flow in the discharge channel and the turbidity level at the discharge point throughout the rain event. Early in the storm, the turbidity level remained below the turbidity standard of 250 NTUs, but as the heavy rains continued, the flow across the Site and into the sedimentation basin increased such that turbidity readings in the afternoon on September 30, 2010 and on October 1, 2010 were above the turbidity standard.  Subsequent rain events occurred throughout the period from October 4 through 16, 2010.  In order to gain capacity in the basin and in an attempt to keep up with the inflow of stormwater run-off into the basin, discharge from the basin was allowed in a controlled manner through the skimmer even though the turbidity levels were above the standard on some days.    

Water samples (analyzed for total and dissolved lead) were collected at the discharge point on days when turbid discharge took place.  The dissolved lead results (through October 8, 2010) were all below the laboratory detection limit of 1.0 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead results were at or below 50.2 µg/L.  There is not an NPDES standard for total lead.  The very low total and dissolved lead results provide reassurance that even though the turbidity levels were above the performance standard, there was NOT a release of lead from the site that would affect the creek or the river.

USEPA, PADEP, and Throop Borough were regularly kept informed by e-mail on stormwater management activities during the period from September 30  to October 17, 2010 and with PADEP’s concurrence, Gould submitted a formal report to PADEP, once the analytical data for the series of storm events had been received, on October 27, 2010.  (Click here to review the September 30 to October 16, 2010 Stormwater Discharge Report.)  See below for a description of the daily stormwater management activities for the period from September 30, 2010 through October 16, 2010:  

September 30 to October 1, 2010 - The regional storm event that occurred September 30 to October 1, 2010 delivered approximately 5.5 inches of rain to the Marjol Battery Site and the surrounding area (based on rainfall information from the USGS gauging station in Jermyn, PA).  Gould monitored the flow in the discharge channel and the turbidity level at the discharge point throughout the rain event. Early in the storm, the turbidity level remained below the turbidity standard of 250 NTUs (turbidity was 67.1 NTUs at 7:45 am), but as the heavy rains continued, the flow across the Site and into the sedimentation basin increased such that turbidity readings at 1:50 pm on September 30, 2010 and at 8:05 am on October 1, 2010 were far above the turbidity standard (2,446 NTUs and 1,167 NTUs respectively).

Water samples (analyzed for total and dissolved lead) were collected at the discharge point during September 30 and October 1, 2010 turbidity exceedances.   The dissolved lead result was 0.26 µg/L on September 30, 2010 and 0.36 µg/L on October 1, 2010.  The NPDES permit standard for maximum dissolved lead for the Site is 650 µg/L.  The total lead result was 50.2 µg/L on September 30, 2010 and 25 µg/L on October 1, 2010.  There is not an NPDES standard for total lead. 

Although the discharge water was turbid, it was not feasible to stop the discharge because the basin is not designed to hold all of the water from a storm like this one without discharging and water would have overflowed through the emergency spillway. It was safest to allow the discharge to continue through the outlet structure rather than allow the water level to build up and overtop the emergency spillway because even though the spillway is armored with stone, a lot of water passing over it could cause erosion or failure of the berm.

Gould and Throop Borough were in communication throughout the rain event to discuss stormwater management activities at the Site.

With the September 30 - October 1, 2010 storm event over (and therefore no additional flow going into the basin), the skimmer in the basin was flipped on Friday afternoon, October 1, 2010, to stop discharge from the sedimentation basin and a flocculent (Pond Clear) was added to the basin to allow the sediments to settle out.

October 2 and 3, 2010 – There was no discharge from the sedimentation basin.

October 4, 2010 - On Monday, October 4, 2010, at approximately 2 pm, due to the elevated water levels in the basin and the continuing and forecasted rain at the Site, it was determined that if the basin was not permitted to discharge through the skimmer the water level in the basin would rise to the top of the outlet structure and discharge at a higher flow rate through the top of the outlet structure. Therefore, in order to gain capacity in the basin and in an attempt to keep up with the inflow of stormwater run-off into the basin, the skimmer was flipped to allow discharge from the basin in a controlled manner even though the turbidity levels were still above the standard. The turbidity level at the discharge point after 15 and 30 minutes was 297 and 310 NTUs, respectively.

At 3:27 pm, a turbidity reading of 314 NTUs was obtained.  Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at this time.  The dissolved lead result was 0.025 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 12.5 µg/L. There is not an NPDES standard for total lead. 

October 5, 2010 - On Tuesday, October 5, 2010, at 8:10 am, a turbidity reading of 287 NTUs was obtained. 
Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at this time.  The dissolved lead result was 0.17
µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 10.6 µg/L. There is not an NPDES standard for total lead. 

October 6, 2010 - On Wednesday, October 6, 2010, discharge continued through the skimmer.  At 9:00 am, a turbidity reading of 256 NTUs was obtained.   Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at this time.  The dissolved lead result was 0.4 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 9.8 µg/L. There is not an NPDES standard for total lead.  Flow through the top of the outlet structure was occurring when the 9:00 am turbidity reading was obtained. 

October 7, 2010 - On Thursday, October 7, 2010, discharge continued through the skimmer.  At 8:30 am, turbidity readings of 251 and 283 NTUs were obtained.  Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at this time.  The dissolved lead result was 0.56 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 9.3 µg/L. There is not an NPDES standard for total lead.  The water level dropped to a point of 6 to 8-inches below the outlet structure by 8:30 am. 

October 8, 2010 - On Friday, October 8, 2010, discharge continued through the skimmer.  At 8:10 am, a turbidity reading of 188 NTUs was obtained.  Based on this reading, the basin was allowed to continue to discharge. An additional turbidity reading was taken at 1:20 pm; the result was 178 NTUs.  Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at this time.  The dissolved lead result was 0.4 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 5.8 µg/L. There is not an NPDES standard for total lead.  The basin continued to discharge over the weekend.

October 9 and 10, 2010 - Discharge from the sedimentation basin continued over the weekend. 

October 11, 2010 - On Monday, October 11, 2010, discharge continued through the skimmer.  At 9:00 am, a turbidity reading of 95.5 NTUs was obtained.  No samples were taken for total and dissolved lead.

October 12, 2010 - A rain event occurred overnight with a total of 0.76 inches over 6 hours. This information was obtained from a USGS rain gauge located in Jermyn, PA approximately 9 miles northeast of the site.  At 7:35 am, a turbidity reading of 346 NTUs was obtained.  Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at this time.  The dissolved lead result was 0.15 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 15 µg/L. There is not an NPDES standard for total lead.   The skimmer was flipped to discontinue discharge from the sedimentation basin and a flocculant (i.e., Pond Clear) was added to the sedimentation basin to allow the sediments to settle out. 

October 13, 2010 – There was no discharge from the sedimentation basin in order to allow time for the flocculants to help settle out the sediments. 

October 14, 2010 – The skimmer remained in the "no flow" position until 3:00 pm. The water level was just below the baffle near the outlet structure. As rain was forecasted and received (approximately 0.34 inches) the water was allowed to discharge to allow capacity for flow into the basin. Turbidity readings were 324 NTUs at 3:15 pm, 312 NTUs at 3:30 pm, and 287 NTUs at 3:35 pm.  Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at 3:15 pm.  The dissolved lead result was 0.024 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 14.7 µg/L. There is not an NPDES standard for total lead. 

October 15, 2010 – Discharge through the skimmer continued to be allowed in order to gain additional capacity in the basin and to allow the sediment basin to function with the baffle and silt curtain. A turbidity readings of 300 NTUs was collected at 8:15 am. Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at this time.  The dissolved lead result was 0.037 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 12 µg/L. There is not an NPDES standard for total lead. 

October 16, 2010 – Discharge through the skimmer continued to be allowed in order to gain additional capacity in the basin and to allow the sediment basin to function with the baffle and silt curtain. A turbidity readings of 260 NTUs was collected at 11:25 am. Water samples (analyzed for total and dissolved lead) were also collected at the discharge point at this time.  The dissolved lead result was 0.023 µg/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L.  The total lead result was 10 µg/L. There is not an NPDES standard for total lead. 

A report on stormwater management discharge for the period from September 30 through October 16, 2010 was submitted to PADEP on October 27, 2010.  (Click here to review the September 30 to October 16, 2010 Stormwater Discharge Report.)

 

(Click here to go back to the Stormwater Management System page.)

 

 

Page Last Modified Tuesday September 04, 2012 08:53:16 AM

 

tel 570.383.9313 | email layers@advancedgeoservices.com

Send mail to
agc@advancedgeoservices.com with questions or comments about this web site.
Copyright © 2006 Advanced GeoServices