Marjol Battery Site
 
Home

Site Background

Summary of Corrective Measures Implementation (CMI) Process

Post-Construction  Maintenance and Monitoring

Construction  Information (May 2008 to August 2010)

Final (100%) Remedial Design

Air Monitoring

Stormwater Management System

Photo Gallery

Quarterly Progress Reports and CMI Completion Report 

Community Relations

Documents

FAQs

Contact Us

Web Site Map

Stormwater Sampling and Discharge System – During Construction                                (May 2008 to August 27, 2010)  

During construction activities, there was the concern about the possibility of lead attached to soil particles being washed into the sedimentation basin and discharged from the Site.  Several precautions were taken to monitor for this and prevent the release of lead from happening:

  1. BMPs Installed – BMPs (best management practices) such as silt socks, silt fence, and a sedimentation basin with baffle and skimmer were installed to minimize the release of soil particles from the Site.                                                                                                                                                                            
  2. Turbidity readings Collected at Discharge Point - The water discharged from the basin was sampled using a turbidity meter. (Turbidity is the amount of soil particles in the water.)  The turbidity standard in the 100% Design Plan is 250 NTUs.  The turbidity standard for discharge from the Marjol Battery Site was put in place at the request of Throop Borough as a real-time measurement that could be used during construction activities to determine if immediate action needed to be taken versus waiting for analytical results.  Since lead sticks to soil particles, if there was low turbidity in the discharge water, then there would be, at most, a minimal amount of lead in the water being discharged.  (Click here for an explanation of the Turbidity Standard.)                                          
  3. Collect lab data on stormwater – Samples of the discharge water are taken at least monthly and during turbid discharge events and were analyzed for total and dissolved lead to confirm that discharge from the Site did not have elevated lead levels.  (Click here for a picture of water discharging from the basin at the discharge point along the perimeter fence.)

The 100% Design Plan called for stormwater from the clean areas of the Site to be collected in the sedimentation basin. Sediment that was carried along with the stormwater would settle out in the basin, and stormwater collected in the basin would be released to Sulphur Creek under a permit issued by the State of Pennsylvania. During construction of the Final Remedy at the Site, the drainage system was designed so stormwater falling on contaminated areas of the Site did not flow into the basin, but was retained within the contaminated areas by berms.

If there was not enough space for all of the water to be held within the contaminated areas, however, the design provided for the potentially contaminated water to also drain to the sediment basin. Since lead sticks to the sediment, as long as the sediment was kept on the site by allowing it to settle out of the water in the basin, the water could be safely discharged to the river. This sediment could then be excavated and placed into the Containment Area before the final cap was installed. Removal of sediment from the sedimentation basin occurred in April 2010.  In this way, the water was managed so that the lead remained on the site by controlling where the sediment went.  But several times turbid water was discharged from the basin.  Since overflow from the CA went into the basin, and water from the basin went into Sulphur Creek, it was possible for lead from the Site to end up in Sulphur Creek.  That’s why it was important to analyze water samples for dissolved lead whenever the turbidity standard was exceeded in water leaving the site during construction activities.  This was done, and the results showed that even though the turbidity levels were above the performance standard, there was NOT a release of lead from the site that would affect the creek or the river.

 

(Click here to go back to the Stormwater Management System page.)

 

 

Page Last Modified Tuesday October 19, 2010 03:32:37 PM

 

tel 570.383.9313 | email layers@advancedgeoservices.com

Send mail to
agc@advancedgeoservices.com with questions or comments about this web site.
Copyright © 2006 Advanced GeoServices