Marjol Battery Site
 
Home

Site Background

Summary of Corrective Measures Implementation (CMI) Process

Post-Construction  Maintenance and Monitoring

Construction  Information (May 2008 to August 2010)

Final (100%) Remedial Design

Air Monitoring

Stormwater Management System

Photo Gallery

Quarterly Progress Reports and CMI Completion Report 

Community Relations

Documents

FAQs

Contact Us

Web Site Map

Stormwater Sampling and Discharge System – Post-Construction            (August 27, 2010 to present)  

A Final Inspection was conducted at the Marjol Battery Site on August 31, 2010. Based on the inspection, construction of the Final Remedy was determined to be “substantially complete” as of August 27, 2010, and the site is in the post-construction period. All lead-contaminated material at the Site is consolidated in the Containment (cap) Area (CA) and has been covered by the multiple layers of cap materials, so all surfaces of the Site are clean (average lead levels below 500 mg/kg). (Click here for a drawing showing the layers of the cap.)

Stormwater management post-construction is slightly different than stormwater management during construction since the lead-contaminated materials are secure under the cap and there is no longer a concern about a release of lead from the site. (For more information on Stormwater Management During Construction, click here.) There is no longer a separate area for handling water that came into contact with the lead-contaminated materials and all runoff flows to the basin. There is still the need to control sediment, however, until the grassy vegetation is established in the areas that were disturbed by construction activities. In order to keep as much sediment as possible on the site, the stormwater management system at the Site was designed so that sediment that is carried along with stormwater would settle out in the sedimentation basin before discharging into Sulphur Creek via the skimmer.

In addition to being part of the 100% Design Plan for the Site, the stormwater management system at the Marjol Battery Site is maintained and monitored under a permit (NPDES permit) issued by the State of Pennsylvania (Gould Electronics Inc. and SCE Environmental are co-permittees on the NPDES permit for the Site.) The 100% Design Plan called for stormwater discharge monitoring from the Site to be discontinued at the end of construction because at that point the potential for lead to be discharged from the Site was removed. The state permit for the Site will however, remain active until vegetation is established at the Site,

In November, 2010, Gould sent a letter to PADEP requesting information on the requirements for sediment basin discharge management under the NPDES permit.  In PADEP’s response (Click here to review PADEP’s response letter.), it stated that stormwater discharge monitoring is not required on “non-working” (days when there is no earth moving activities).   Gould has elected to continue to test for total and dissolved lead on a monthly basis, even though the potential for lead contamination had been removed once the remedy was complete. Turbidity monitoring will only occur when the basin is discharging while earth moving activities are taking place.  Once vegetation at the Site is established, the amount of soil particles being washed away in stormwater should be much less and therefore the potential for turbid discharge should be substantially decreased.

(Click here to go back to the Stormwater Management System page.)

 

Page Last Modified Friday March 04, 2011 09:52:06 AM

 

tel 570.383.9313 | email layers@advancedgeoservices.com

Send mail to
agc@advancedgeoservices.com with questions or comments about this web site.
Copyright © 2006 Advanced GeoServices