Marjol Battery Site
Major Milestone Reached – Remedy Construction is Complete! For more information, see the Construction Schedule and Information page of the web site.
 
Home

Site Background

Summary of Corrective Measures Implementation (CMI) Process

Construction Schedule and Information

Final (100%) Remedial Design

Air Data

Stormwater Management System

Photo Gallery

Quarterly Progress Reports & Monitoring

Community Relations

Documents

FAQs

Contact Us

Web Site Map

STORMWATER DISCHARGE ABOVE THE PERFORMANCE STANDARD - MARCH 30 and 31, 2010

Over 1.5 inches of rain was received on March 30, 2010.  The skimmer had been flipped to prevent water from leaving the basin.  (Click here for Stormwater Sampling and Discharge information)  When SCE and AGC representatives checked the Site in the evening during the rain event, there was flow coming from the discharge pipe due to a leak in the skimmer arm.  AGC took a turbidity reading at the discharge point and the result was 77.5 NTUs at 7:30 pm.  (Turbidity is a measurement of the cloudiness of the water which is caused by sediment.)  The basin had filled up to the point of almost going over the baffle, so AGC representatives flipped the skimmer to allow water to discharge from the basin.  Shortly after flipping the skimmer, AGC checked the turbidity at the discharge point.  The turbidity was 330 NTUs at 8:45 pm.  The turbidity level is supposed to be below 250 NTUs for discharge, so AGC flipped the skimmer back into the closed position to stop water from flowing into the discharge channel.  There continued to be some flow in the channel due to the leak in the skimmer arm. 

On March 31, 2010, a turbidity reading was collected at the discharge point at 8:45 am.  The turbidity result was 330 NTUs. A turbidity reading of 324 NTUs was collected at the discharge point at 9:30 am after additional BMPs (hay bales) were added in the channel outside the fence.  Turbidity at the confluence of the discharge channel and Sulphur Creek was checked as well.  Two turbidity readings were taken at this location: one was 152 NTUs and the other was 158 NTUs.  This demonstrated that while compliance with the performance standard was not achieved at the discharge point, it was met before the water entered Sulphur Creek.  As requested by AGC, SCE plugged the skimmer orifice inside the outlet structure around the skimmer orifice plate.  Once the plug was in place, flow into the discharge channel was reduced by approximately 90%.  AGC observed that by approximately 1 pm, all flow in the discharge channel had stopped.   

Water samples (one for total lead and one for dissolved lead) were collected from the discharge point and were sent to the laboratory for analysis.  The dissolved lead result was 4.4 ug/L.  The NPDES permit standard for maximum dissolved lead for the Site is 650 ug/L. The total lead result was 33.9 ug/L. There is not an NPDES standard for total lead, but the total lead result will be compared to the turbidity levels and then to the dissolved lead result.  The very low total and dissolved lead results provide reassurance that even though the turbidity levels were above the performance standard, there was NOT a release of lead from the site that would affect the creek or the river.

The skimmer and orifice were repaired during the week of April 5, 2010, to prevent further leaks into the structure.

EPA, DEP, and Throop Borough were notified of the turbid discharge.  As is required, a non-compliance report was submitted to PADEP on April 6, 2010.  (Click here to review the Non-Compliance Report.)

 

502 George Street | Throop, PA 18512 | tel 570.383.9313 | fax 570.383.9309 | email layers@advancedgeoservices.com

Send mail to
agc@advancedgeoservices.com with questions or comments about this web site.
Copyright © 2006 Advanced GeoServices